Salt Shed – District 4

Neighborhood: Brighton
Description: PWD Bridges and Buildings Division was tasked with designing a salt shed for the District 4 yard in Brighton to protect the salt pile from the elements. PWD constructed a 70’x75’ salt shed at District 4 yard located on 315 Western Avenue. The pre-engineered structure consisted of aluminum parts to prevent erosion and the structure was placed on top of a precast concrete blocks foundation. The site work and foundation layout were performed by PWD Staff and the Structure was installed by WES Construction.
Project Status: Completed
Project Cost: $400,000
Project Completion: August, 2013
Project Team:
- Fouad Hamzeh, Project Manager, BPWD
- FST, Design Consultant
- WES Construction Co., Contractor